Category: Oil & Gas

SIX WEEKS BEFORE STARTUP:
A FUNCTIONAL SAFETY ASSESSMENT ON AN LNG PROJECT

Summary →

An LNG operator commissioned a pre-startup functional safety assessment on a new processing train. The assessment found the safety lifecycle substantially complete and the evidence for it scattered across four organizations. Startup was not delayed.

At a Glance →
ChallengeSolutionResult
Safety lifecycle evidence dispersed across operator, EPC, vendor and integrator. Pre-startup functional safety assessment with a consolidated safety case. Assessment closed before commissioning, with a single defensible evidence package.

Project Background

The operator was six weeks from commissioning a new LNG processing train delivered by an engineering, procurement and construction contractor, with the safety instrumented system supplied by one vendor and configured by a separate integrator. The operator required a functional safety assessment before startup, as IEC 61511 expects at that stage of the lifecycle. The question was not whether the engineering had been done competently. It was whether the operator could demonstrate it had, using evidence it actually held, on the day a regulator or an insurer asked.

Challenge →

On a capital project of this structure, the safety lifecycle is executed by four organizations and the evidence ends up living wherever each organization filed it. The hazard analysis sat with the operator. The SIL determination sat partly with the operator and partly with the EPC contractor. Device certification and failure data sat with the vendor. Logic configuration, factory acceptance testing and site acceptance testing records sat with the integrator. Each party held a coherent set of records for its own scope and nobody held a continuous chain across the lifecycle.

That fragmentation creates a specific problem at the pre-startup assessment, which is not an engineering review but a demonstration of lifecycle completeness. The assessor has to confirm that the hazards identified at the start are addressed by the functions specified in the middle and verified by the testing at the end, with traceability between them. A gap anywhere in that chain cannot be closed by any one organization, because none of them can see the whole chain.

The timeline made the work unusual. Six weeks before commissioning, the remedy for a finding cannot be an engineering change in most cases. It has to be either documentation that already exists and has not been collected, or a defensible operating restriction carried into startup and resolved later. Distinguishing those two categories quickly was the central task, because an assessment that produced a long undifferentiated finding list at that point in a project is unusable.

Solution →

Arista Cyber ran the assessment to triage findings by what could actually be done in the time available, consolidating evidence across all four organizations into a single traceable chain.

01

Lifecycle Scope Definition

Established which lifecycle phases the assessment would cover and which organization held the evidence for each.

02

Evidence Collection

Gathered records from operator, EPC contractor, vendor and integrator into one controlled set, identifying what was missing rather than absent.

03

Traceability Verification

Confirmed each identified hazard traces to a specified safety function, a verified SIL and a completed test record.

04

Finding Triage

Sorted findings into documentation gaps, verification gaps and engineering gaps, because each has a different remedy and a different timescale.

05

Pre-Startup Closure

Closed documentation and verification gaps by collecting or generating the missing evidence before commissioning.

06

Residual Item Management

Converted the small number of items unresolvable before startup into documented operating restrictions with owners and target dates.

07

Safety Case Consolidation

Delivered a single safety case the operator holds, independent of the contractors who will demobilize after commissioning.

Result →

The functional safety assessment was completed before commissioning and the train started up on schedule. The operator holds a consolidated safety case covering the full lifecycle, with traceability from each identified hazard through to the test record demonstrating the corresponding function works.

The triage step was what made the timeline achievable. The large majority of findings were documentation gaps: evidence that existed inside one of the four organizations and had simply never been transferred to the operator. Those closed by collection rather than by engineering, which is fast. A smaller set were verification gaps, where a calculation or a test record was genuinely absent and had to be produced, which was achievable in the window because the underlying engineering was sound. Only a handful were engineering items, and those became documented operating restrictions carried into startup with named owners and dates rather than open questions.

The consolidation has a value that outlasts the project. Contractors demobilize after commissioning, and the window in which their records can be obtained closes with them. An operator that reaches its first regulatory inspection or its first safety-related incident holding a complete lifecycle evidence package is in a materially different position from one that must request records from an EPC contractor years later. The operator also now has the baseline against which future modifications are assessed, which means the next management of change starts from a documented position rather than reconstructing one.

Who Should Engage Arista Cyber?

Operators approaching startup on a capital project who need a functional safety assessment, those whose lifecycle evidence is dispersed across EPC contractors, vendors and integrators, and anyone who will lose access to contractor records at demobilization.

What's the Next Step?

Approaching startup and unsure whether your safety lifecycle evidence is complete? Contact Arista Cyber to scope a functional safety assessment.

  • Commission a pre-startup functional safety assessment
  • Request a safety case consolidation before your contractors demobilize
  • Schedule a functional safety lifecycle assessment
BOOK YOUR CONSULTATION